Pool renovation is underway!

For more than a decade, families across the South Shore have made Weymouth Club their go-to place for swim lessons in Weymouth, MA, whether they’re learning, training, staying fit, or just making a splash. Our pool is the home of lap swimming, competitive swimming, water fitness classes, and lifeguard training, plus year-round family swim fun.

Our pool renovation is underway, with the grand opening planned for June 2027. When it’s complete, swimmers will enjoy a larger pool deck, outdoor showers, indoor restrooms, and a dedicated area where our youngest members can enjoy the water safely.

The Timeline

  • September 2026 – The project kicked off just after Labor Day with demolition.
  • October 2026 – Demolition was completed and the pool forms were built to prepare for shotcrete (pool shell).
  • November 2026 – Piping & plumbing will be installed. Shotcrete will be poured to form the pool shell.
  • December 2026 – We will backfill piping and plumbing trenches along with further construction of the deck. We will also winterize in preparation for January & February.
  • Late March 2027 – We will prepare the pool for plaster and tile work, as well as continue plumbing work.
  • April 2027 – We will prepare the pool deck and drain system. We will also  plaster and tile the pool.
  • May 2027 – We will install filter and heating equipment, pour decking around the pool, install finishes & furniture.
  • June 2027 – We will celebrate our Grand Opening!